McNatt Shelter Construction Process

Construction on the McNatt facilities continues to progress. As of this week, 80% of the steel is up, and should be completed in the next 2 weeks. Work continues on the plumbing and electrical under the slab for the panels. Work will begin in the next two weeks on the dumpster pad and setting the light pole bases. Masonry work will mobilize as well. Below are pictures from October 2013 through this week: